Essar Starts Production After 6 Yrs
After a delay of close to 6 years, Essar Oil's Jamnagar refinery has finally begun production. The plant started trial production with a capacity of 7.5 million tonnes per annum of crude and the company expects to attain production at full capacity in the next two quarters, a company statement said. "We are delighted at the successful commissioning of the refinery at a time when India is strengthening its presence in global markets and integrating with the global economy," chairman of Essar Group Shashi Ruia said.
The company, which faced a massive cost overrun due to the delay in commissioning \_ said its project cost of Rs 10,826 crore is extremely competitive and lower than estimated costs for a green field refinery.
Essar Oil had came out with one of India's biggest initial public offer of shares in the early nineties and most of its investors saw their capital eroding. Financial institutions, which had lent funds to the company, had to take a huge cut in interest to salvage the project. Both Reliance and Essar started work at jamnagar at the same time but Reliance started production on the scheduled date while Essar blamed a cyclone for the delay in the commissioning of the project.
--
Brip
–
Brip